Contract No. HY/2000/21 - Route 8 Ngong Shuen Chau Viaduct





Overview of Completed Bridge Spans at P1-SA6





LG1 Reassembled at Grids 31 and 32





LG1 Reassembled while LG2 was being Transported to Grid 30





Construction of Ramp E Abutment Substantially Completed





Overview of Construction Works at Roundabout CP3/CP4





Construction of Portal NSB25 Completed





Laying of 1200mm Stormwater Drain between Manholes SM6.26 and 6.31





Second Segment Pair Installed by Lifting Beam at Pier NSB22





Construction of Abutment F1-19(M) in Progress





Segment Erection of Bridge E1A by Crane at Pier E1-17





Construction of Ramp E1 Abutment in Progress





Construction of T-Pier NSB15 in Progress





Scaffolding Installed for Portal Construction at Grid 11, and Self-Climbing Formwork was being Assembled at Grid 9





Construction of Booster Pump House in Progress





High Rise Column Construction at Grid 6





Portal Construction at Grid 4 in Progress