Contract No. HY/2000/21 - Route 8 Ngong Shuen Chau Viaduct





Overview of Completed Bridge Spans at P1-SA6





Segment Erection of Bridges ML9 and ML10 at Grid 30 by LG2





Panoramic view of LG2 at Grid 30





Overview of Construction Works at Roundabout CP3/CP4





Construction of T-Pier at Pier NSB23 and Crosshead at Pier F1-23 in Progress





Segment Erection of Bridge EB at Pier E13 by LG1





Pier Segment Installed at Pier F12





Construction of Ramp F1 Abutment in Progress





Second Segment Pair being Installed by Lifting Beam at Pier NSB17





Construction of Ramp E1 Abutment in Progress





Construction of T-Pier NSB15 in Progress





Construction of Portal at Grid 11 in Progress





Construction of Portal at Grid 11 in Progress





Overview of Construction Works at P1-SA1, viewing East from Grid 8





Construction of Booster Pump House in Progress





Portal Construction at Grid 4 in Progress